1.
Material Cost Variance :-
(SQ x SP) – (AQ x AP) 

(Standard Quantity x Standard Price) – (Actual Quantity x Actual Price)


2.
Material Price Variance: -
(SP- AP) x AQ

(Standard Price - Actual Price) x Actual Quantity


3.
Material Usage Variance :-
(SQ - AQ) x SP

(Standard Quantity - Actual Quantity) x Standard Price


4.
Material Mix Variance: -
(RSM- AQ) x SP

(Revised Standard Mix - Actual Quantity) x Standard Price


4.1
Revised Standard Mix: -
S Q x TAQ
TSQ


Standard Quantity x Total Actual Quantity
Total Standard Quantity


5.
Material Yield Variance: -
(A.O - RSY) x SC

(Actual Output - Revised Standard Yield) x Standard Cost per unit of output


5.1
Revised Standard Yield: -
A.O x TAQ
TSQ


Actual Output   x Total Actual Quantity
Total Standard Quantity


5.2
Standard Cost per unit of output:-
T.S.C
A.O

Total Standard Cost
Actual Output



5.2.1
Total Standard Cost:-
(SQ x SP)

(Standard Quantity x Standard Price)



6.
Verification :-


MCV = MPV + MUV


Material Cost Variance = (Material Price Variance + Material Usage Variance)


7.
 Labour Cost Variance :-
(SH  x SR) – (AH x AR)

(Standard Hours x Standard Rate) – (Actual Hours x Actual Rate)


8.
Labour Rate Variance :-
 (SR - AR) x AH

(Standard Rate –Actual Rate) x Actual Hours


9.
Labour Efficiency Variance :- 
(SH - AH) x SR

(Standard Hours - Actual Hours) x Standard Rate


10.
Labour Mix Variance: -
(RSM- AH) x SR

(Revised Standard Mix - Actual Hours) x Standard Rate


10.1
Revised Standard Mix: - 
 S H x TAH
TSH

Standard Hours   x Total Actual Hours
Total Standard Hours


11.
 Idle Time Variance:- 
(IT x SR)

(Idle Time x Standard Rate)



12.
Labour Yield Variance: -
 (A.O - RSY) x SC

(Actual Output - Revised Standard Yield) x Standard Cost per unit of output


12.1
Revised Standard Yield: -
A.O x TAH
TSH




Actual Output  x Total Actual Hour
Total Standard Hours


12.2
Standard Cost per unit of output:-
T.S.C
A.O

Total Standard Cost
Actual Output



12.2.1
Total Standard Cost:-
(SH  x SR)

(Standard Hours x Standard Rate)



13.
Verification :-


LCV = LRV + LEV + ITV


Labour Cost Variance = (Labour Rate Variance + Labour Efficiency Variance + Idle Time Variance)